Marlowe & Voss · The Ashgrove Hotel

04 / 06

Section three

Delivery plan

Fourteen months, eight milestones, and the hotel takes bookings on every one of them.

Measured survey and archival research

Full point-cloud survey, paint scrape analysis, and the layer drawing.

Duration: 4 weeks

Position paper agreed

Signed off with you and with the conservation officer. No design begins until it is agreed.

Duration: 3 weeks

Concept design, five room typologies

One typology developed far enough to build rather than to present.

Duration: 6 weeks

Sample room built and reviewed on site

Built in room 214. Everything is tested here before it is repeated forty-one times.

Duration: 3 weeks

Technical design and schedules issued

Joinery, lighting, textiles and finishes resolved to installation level.

Duration: 8 weeks

Floor three: strip, build, install

Fourteen rooms. The hotel trades on floors one and two throughout.

Duration: 9 weeks

Floors two and one, and the Long Room

Twenty-eight rooms and the dining space, sequenced against occupancy.

Duration: 16 weeks

Colonnade and handover

Garden works, snagging, and a maintained finishes manual left with your team.

Duration: 4 weeks